UPS Planned Maintenance UPS batteries verification - Data Center MCL
Scheduled Maintenance Report for iWeb Status Page
Completed
The scheduled maintenance has been completed.
Posted 3 months ago. Jan 25, 2017 - 15:30 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 3 months ago. Jan 25, 2017 - 07:00 EST
Scheduled
(EN) Scheduled Maintenance: UPS batteries verification.

Location: MCL

Start (yy/mm/dd) : 2017/01/25 7:00AM
End (yy/mm/dd) : 2017/01/25 3:30PM
Duration: 8h30

Impact: None expected

Hi,

Please note that a maintenance is scheduled on the UPS units on data center MCL, on January 25th 2017.
Only one UPS will be worked on at a time.

If you have any questions, do not hesitate to contact us at http://iweb.com/contact

********************************************************
(FR) Entretien planifié: Vérification des batteries d'UPS.

Lieu: MCL

Début (aa/mm/jj): 2017/01/25 7h00
Fin (aa/mm/jj) : 2017/01/25 15h30
Durée: 8h30

Impact: Aucun prévu

Bonjour,

Veuillez noter qu’un entretien est prévu au niveau des UPS du centre de données MCL, le 25 Janvier 2017.
Nous allons travailler sur un seul UPS à la fois.

Si vous avez des questions, n'hésitez pas à nous contacter http://iweb.com/fr/contact

********************************************************
(ES) Mantenimiento planificado: Verificacion de las baterias en el UPS

Lugar: MCL

Inicio (aa/mm/jj) : 2017/01/25 7:00AM
Fin (aa/mm/jj) : 2017/01/25 3:30PM
Duracion: 8h30

Impacto: Ningún impacto previsto

Hola,

Por favor tome en cuenta que un mantenimiento esta planeado a nivel de un UPS del centro de datos MCL, los días 25 de Enero.
Tome en cuenta que solo un UPS estará en funcionamiento a la vez.

Si tiene alguna pregunta, no dude en contactarnos: http://es.iweb.com/contactos/
Posted 4 months ago. Jan 04, 2017 - 18:26 EST